[Steam-engine] email from state boiler inspector
Eric Applegate
eric at glassactonline.com
Sat Oct 22 15:05:18 PDT 2005
Dang can't ask for more than that. Attitude is everything. Makes me want to move to the Big Sky. Sounds like you found a friend on the inspection board and things could't be better. I'm tickeled for you hope it all works out well.
Eric
---------- Original Message ----------------------------------
From: "Richard Strobel" <Richard_Strobel7 at msn.com>
Reply-To: Steam-engine mailing list <steam-engine at lists.stationary-engine.com>
Date: Sat, 22 Oct 2005 10:31:02 -0600
>G'day all;
> The below is an email from the state boiler inspector regarding the
>proceedure he will use to access our boiler..might be helpful info for the
>newbee:
>
>Rick,
>
>
>The following is an outline of the procedure we will follow to evaluate and
>compute the pressure capabilities of your fire-tube vertical boiler
>(Manufacturer unknown).
>
>Pre Hydrostatic Procedure- The State of Montana will perform ultra-sound
>metal thickness testing on your boiler at no cost to you, to determine metal
>thickness at various random locations. The data produced will be used to
>calculate the maximum allowable water pressure
>(MAWP) of your boiler.
>
>Hydrostatic test Procedure- Upon successful completion of the ultrasound, a
>hydrostatic test will be performed as per Section One of the ASME code
>(Power Boilers) and the NBIC (National Board Inspection Code) Appendix C, to
>determine vessel integrity.
>
>If the boiler passes the hydrostatic test we can proceed with the fitting of
>Boiler safety devices and accessories to meet State Codes.
>
>Rick, I think this will be a great project and am looking forward to working
>with you and Corky!
>_______________________________________________
>Steam-engine mailing list
>http://www.stationary-engine.com/mailman/listinfo/steam-engine
>
More information about the AT