James,

Generally designed by the company building them.most of them had averaged around 2000 man hours per unit for assembly, paint, startup and testing. Part fabrication was subcontracted. Examples are Frac pumps, cement units, blending units, etc.
I have been part and lead of teams for cost reduction at various times. The biggest impact was generally design changes to reduce part cost, and sometimes make assembly easier.

Dennis


Sent from my iPad

> On Nov 30, 2019, at 6:21 PM, James Peck <jamesgpeck at hotmail.com> wrote:
> 
> Were those oilfield units designed by the group that built them or by another organization.
> 
> Dennis Johnson AT List Member (moscowengnr at outlook.com); I have had various experiences with “Lean”. It worked well on oilfield units that had a production rate over 36 units per year. With smaller volumes like 3 or 4 units per year it mainly caused management frustration.  Toyota uses this for their auto production, but probably not for their race car program. 
> _______________________________________________
> AT mailing list
> AT at lists.antique-tractor.com
> http://lists.antique-tractor.com/listinfo.cgi/at-antique-tractor.com


More information about the AT mailing list