wrote:
> 7 days minimum but still suggest you wait the full 28
> days..........concrete cure time is 3, 7, and 28 days........wait it out
> it will last
> forever.....if you get on it too early you will do it over.....I am not
> sure prices there but here is 105.00 per cubic yard.......that's 9 x 9 x
> 4 inches deep
>
> Too much money for me to mess around with
>
> Frank
>
You are 100% correct, Frank. I have always waited 14 days to park stuff on
it till this time. I put stuff back in Friday (12 days) as we have had 2+"
of rain this weekend. Anything over 10,000 lbs needs to wait the 28 days.
To drive a car over it - with a good base under it, I would wait the 7 days
at least / 14 if I had a good way around it. The full month for a heavy
truck.
-steve